Construction update July 2015

The environmental impact assessment was approved on August 2013.

Construction has already started since September 2013

Summary construction progress as follows :

Construction update July 2015

The environmental impact assessment was approved on August 2013.

Construction has already started since September 2013

Summary construction progress as follows :

Weight Percentage 
  Completed  

   Work has progressed up to

1.Pilling Work        6%       100.00 % Finish
2.Super Structure Work      23%       100.00 % Finish
3.Architectural Work      32%         100.00 % Finish
4.Interior Work      13%         100.00 % Finish
5.Electrical and communication      12%         100.00 % Finish
6.Sanitary Systems        6%       100.00 % Finish
7.Ventilation Systems        7%       100.00 % Finish